Lindberg Avenue

Lindberg Avenue Project consisted of improved drainage and detention area in the beautiful City of McAllen. This high profile project was originally scheduled for 90 days, however, TCC attacked the job aggressively and completed the project in less than 65 days. Work included excavation and haul off, relining and regrading a concrete lined canal, re-establishing …

Lindberg Avenue Read More »

Yuma Expansion Project

Yuma Road consisted of rerouting an existing irrigation canal to install a siphon across the proposed roadway. This delicate operation was completed safely and efficiently. TCC coordinated with the owner to execute this operation flawlessly. The Yuma Road expansion project consisted of abandoning and obliterating an existing roadway and constructing a new roadway on new …

Yuma Expansion Project Read More »